Text
1. The Defendant’s KRW 97,800,000 as well as the Plaintiff’s annual rate of KRW 5% from July 29, 2017 to August 3, 2018.
Reasons
1. The Plaintiff: (a) supplied materials for plastic houses at the Defendant’s construction site from January 2017 to June 2017; and (b) around June 17, 2017, the Defendant: (c) provided the Plaintiff with a loan certificate stating that the said materials price of KRW 70 million shall be KRW 30 million on June 28, 2017; (d) KRW 20 million on July 15, 2017; and (e) paid KRW 27 million on July 28, 2017 to the Plaintiff in installments; and (e) provided the Plaintiff with the said materials worth KRW 27 million on June 28, 2017; and (e) provided the Plaintiff with the said materials worth KRW 7 million on June 28, 2017; and (e) provided the Plaintiff with the said materials worth KRW 7 million on June 17, 2017; (e) the Defendant did not pay the said materials to the Plaintiff as KRW 7 million.
2. Article 208 (3) 3 of the Civil Procedure Act (Judgment by public notice) of the applicable provisions of Acts;