Text
1. The Defendant (Counterclaim Plaintiff) shall pay the following money to the Plaintiff (Counterclaim Defendant) A corporation:
(a) 57,201,469 won;
(b) above;
Reasons
1. The table of a written judgment on basic facts (common of main and counterclaims) was attached in attached Form 1. A.
1) Plaintiff A Co., Ltd. (hereinafter referred to as Plaintiff A Co., Ltd. and the Defendant, as part of the determination of the principal lawsuit and counterclaim between Plaintiff A Co., Ltd. and the Defendant, are “Plaintiff A” or “Plaintiff”.
(2) The Defendant’s trade name was changed from “Stock Company D” to “Stock Company C” on November 8, 2016.
(2) Each contract agreement between the Plaintiff and the Defendant was drawn up between the Plaintiff and the Defendant, with the Plaintiff as the contractor, as set out below:
(1) The term “E Corporation”, “F Corporation”, and “F Corporation”. The term “the construction works” are 13,200,000 won and 13,20,000 won and 320 won and 154,000 won and 154,00,000 won and 154,00,000 won and 13,000 won and 13,20,000 won and 320,000 won and 154,00,000 won and 154,00,000 won and 10,000 won and 13,00 won and 13,00 won and 1,000 won and 1,00 won and 1,00 won and 2,00 won and 2,00 won and 2,00 won and 2,00,00 won and 2,00 won and 1,000 won
B. The Defendant paid the construction price to the Plaintiff as indicated below [Attachment 2].
(4) Of 10,00,000 won 1.10,000, 77,000 won, 20.30,000 won, 20.15,00 won, 10,000 won, 20.30,000 won, 20.30,000 won, 20.30,000 won, 10,000 won, 30,000 won, 10,000 won, 10,000 won, 10,000 won, 30,000,000 won, 10,000 won, 30,000, 30,000 won, 30,000 won, 16, 50,000, 30,000 won, 10,000 won, 10,000 won, 300, 105, 2010