logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 대구지방법원 2016.06.02 2015나16161
공사대금
Text

1. The defendant's appeal is dismissed.

2. The costs of appeal shall be borne by the Defendant.

Purport of claim and appeal

1...

Reasons

1. The parties' assertion

A. On February 13, 2015, the Defendant contracted the Plaintiff with the Changho Construction Costs of KRW 16,000,000 among the new construction works of Seongbuk-gu Seoul Building (hereinafter “instant building”). As such, the Defendant is obligated to pay the Plaintiff the said construction cost of KRW 16,00,000,000 and damages for delay.

B. In relation to the construction of the instant building, the Defendant entered into a contract for construction works, such as the structure, steel bars, and electricity, with ELS Co., Ltd. on May 2, 2014, and entered into a contract for construction works with ELS on April 29, 2014, and entered into a contract for construction works, such as tegry, tegical, and Changho, with D on April 29, 2014

2. Comprehensively taking into account the overall purport of arguments and arguments as to Gap evidence Nos. 1 through 7 (including paper numbers; hereinafter the same shall apply), Eul evidence Nos. 1 and 2, the defendant entered into a subcontract for construction of the building of this case with the E Design No. 701,80,000 won (representative D) and the construction cost No. 701,80,000 won on April 29, 2014, May 2, 2014; ② the above D entered into a subcontract for construction amount of 60,000,000 won on September 15, 2014 with the plaintiff on September 15, 2014; ③ the defendant entered into a subcontract for construction amount of 2,40,000 won on February 13, 2015 with the plaintiff on February 13, 2015 and additional facts as to the construction cost No. 1301,05,015 won on each of the building of this case.

On February 13, 2015, the defendant requested D to prepare a written agreement in preparation for cases where additional construction or incidental expenses occur to F children of the defendant, who kept the defendant's seal imprint registration book at the time of the time, and F to obtain the defendant's seal imprint from F, respectively, in documents where both the agreement and name of the construction site, construction cost, construction cost, ordering person and recipients are official seals, and the plaintiff's seal imprint No. 2 is written in the above official column.

arrow