(영문) 대구지방법원 2016.10.26 2014가단124330
구상금
Text

1. The Defendants are jointly and severally liable to the Plaintiff for 72,907,083 won and 5% per annum from February 8, 2014 to October 26, 2016.

Reasons

1. On November 4, 2013, the Plaintiff entered into an insurance contract with respect to the buildings, facilities, fixtures, fixtures, and movables at the E store located in the Gyeongsan-si (hereinafter “the subject matter of the instant insurance”) with the following content:

Insurance types: 1309 policyholders, and insured workers, regardless of internal business: From November 4, 2013 to November 4, 2018, the insurance coverage period was 100,000,000 total of the building with the total purchase amount of insurance coverage of 1,00,000,000 unit fixtures total of 2,00,000,000 unit unit fixtures and unit fixtures total of 300,000,000,000 aggregate total of 30,000,000,000,000, and the purchase amount of insurance coverage (hereinafter referred to as “Defendant Company”) were transferred from the Non-Party Associate Design Research Institute (hereinafter referred to as “Non-Party Company”) to 15,00,000 (hereinafter referred to as “Defendant 2”) and the 15,000,000 roof and unit of the building of this case; Defendant 1 (hereinafter referred to as “Defendant 2”).

(hereinafter referred to as the “instant fire.” The roof and wall board of the instant building were partly posted by the instant fire, and the facilities and office fixtures inside the instant building were partially destroyed by the heat and studios caused by the instant fire, and the fire caused by the fire, and the house fixtures. The clothes, etc. in the first floor store and warehouse in the instant building, and the second floor warehouse were partly damaged by the fire-fighting waterways that were sprinked for smelling caused by noise and heat and extinguishing fire.

On November 6, 2013, the Plaintiff: (a) requested the instant fire damage adjustment company (hereinafter “hockco damage adjustment”); and (b) the guardianco damage adjustment was made on November 6, 201 on the part of the building.