Text
1. The part of the plaintiff's succeeding intervenor's claim that exceeds the amount ordered by Paragraph 2. shall be dismissed.
Reasons
1. Circumstances leading to the dispute of this case;
A. Contract 1 between the Plaintiff and D) The forest E (hereinafter “the forest of this case”) in the Shinan-gun (hereinafter “the forest of this case”).
(D) On May 23, 2003, D obtained a permit from the head of the Newananananan District to build accommodation facilities in the name of “F” in the instant forest (No. 1-3), and thereafter entered into a sales contract with the Plaintiff (i) (i) (ii) obtained a permit for conversion of a mountainous district for the purpose of “new construction of theG” with respect to the instant forest from December 26, 2007 to November 30, 2013 (i) obtained a permit for conversion of a mountainous district for the purpose of “new construction of theG” with respect to the instant forest from the head of the Newananan District, (ii) obtained a permit for conversion of a mountainous district from December 26, 2007 to November 30, 2013 (hereinafter “Plaintiff”) with the Plaintiff (hereinafter “Plaintiff”) on behalf of the husband of D on June 22, 2013 and (iii) to purchase KRW 200,000,00.
(A) On July 16, 2013, the Plaintiff awarded a contract to the Defendant for blasting, etc. on the instant forest and land, other than KRW 10,267 square meters (Evidence 1-1-2). On the end of the said contract, the Plaintiff entered into a sales contract with H representing D on August 7, 2013 and approximately KRW 200,000 cubic meters of the earth and rocks to be additionally collected in the instant forest and land, including KRW 10,267 square meters (Evidence 1-1-2). In the end of the said contract, the Plaintiff entered into a sales contract with H on August 7, 2013, stating that “A contract with the Plaintiff and J shall be reversed, and the Defendant shall be recognized as the Defendant.”
(No. 12) . Indication of the above sales contract - The aggregate of the purchase price shall be KRW 1.1 billion on the condition that the buyer bears all the expenses necessary for blasting and for the forembing of the soil and rocks (see about KRW 200,000 cubic meters in total, about 300,000 cubic meters) to be additionally collected at the same place and the soil and rocks (see, e.g., confirmation of the designer, about KRW 200,00,000 in cubic meters) to be collected from the forest of KRW 12,00,000 in neighboring three places after collecting from the forest of KRW 1,00,000,000,000 in total.
(excluding value-added tax).