(영문) 서울행정법원 2018.10.12 2018구합63990
관리처분계획 무효확인
Text

1. All plaintiffs' lawsuits are dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

1. Details of the disposition;

A. The Defendant obtained authorization for the establishment of a housing redevelopment project from the head of Songpa-gu Seoul Metropolitan Government (hereinafter “the head of Songpa-gu”) on February 6, 2009 to implement the housing redevelopment improvement project in Songpa-gu Seoul Special Metropolitan City J (hereinafter “instant rearrangement zone”) and obtained authorization for the establishment on February 10, 209, and obtained authorization for the establishment change on July 20, 2012, and the Plaintiffs owned real estate, such as land in the instant rearrangement zone.

B. On March 20, 2014, the Defendant received the application for parcelling-out from the members for parcelling-out after having received an authorization to implement the project on August 12, 2013, setting the period for application for parcelling-out from March 24, 2014 to April 30, 2014, and making an announcement of the period for application for parcelling-out, and extended the period for application for parcelling-out to May 20, 2014. The Plaintiffs did not apply for parcelling-out within the said period for parcelling-out.

C. The Defendant: (a) formulated a management and disposal plan to classify the Plaintiffs as persons subject to cash settlement and exclude them from persons subject to sale; and (b) on April 27, 2015, the head of Songpa-gu publicly announced that the above management and disposal plan was approved; and (c) on April 30, 2015, the head of Songpa-

(hereinafter “instant management and disposition plan”) D.

The defendant shall establish a plan to revise the management and disposal plan that changes the details of the existing management and disposal plan, such as adjusting total project costs, and shall obtain approval from the head of Songpa-gu on August 23, 2017 (hereinafter referred to as "the first management and disposal change plan"), formulate a plan to revise the management and disposal plan again after re-approval of the plan to revise the management and disposal plan (hereinafter referred to as "the second management and disposal change plan"), and formulate a plan to revise the management and disposal plan again on January 26, 2018 from the head of Songpa-gu (hereinafter referred to as "the second management and disposal change plan"), and formulate a plan to revise the management and disposal change plan again on May 17, 2018.