All appeals by the plaintiffs are dismissed.
The costs of appeal are assessed against the plaintiffs.
The purport of the claim and the appeal shall be 1.
Reasons
1. Facts of recognition;
(a) Business Recognition and Public Notice - Business Name: C Urban Development Project (hereinafter referred to as the “Projects in this case”) - Public Notice of Business Recognition: J-Public Notice of the Ministry of Land, Infrastructure and Transport’s 18 May 2012: The date of public announcement of Development Project Inspection: April 21, 2008
B. Adjudication on expropriation by the Central Land Expropriation Committee on November 10, 2016 - Land to be expropriated: Six parcels, such as Gyeyang-gu E, Soyang-gu, the Plaintiff owned, and twelve parcels, such as Plaintiff B-owned F (hereinafter collectively referred to as “the instant land,” the same as the attached Form; hereinafter the same shall apply) - The date of commencement of expropriation: January 3, 2017.
The ruling of the Central Land Expropriation Committee on June 22, 2017 - Compensation for losses: Plaintiff A20,244,926,560, Plaintiff B8,05,520,920 won
(2) The difference in the publicly announced land prices in 2008 between Q 670,00 won 886,900 won 216,000 won 32.3721% T 630,000 won 761,000 won 1339% S 20.7939% 450,000 won 359,000 31,429,000 31,429,000 31,429,000 370,95,000 995,000 220,200 2209,209, 2000 - 370, 208, 2000 - 1,208 of the appraisal land prices in green areas or green area - the appraisal land prices in the same manner as the plaintiffs - 1,207 appraisal land prices in green area - - - 3.