Text
1. As to the temporary buildings listed in the separate sheet:
A. Defendant B Co., Ltd. transfers on June 5, 2002 to Defendant C.
Reasons
1. Indication of claim;
A. On June 5, 2002, Defendant B Co., Ltd. (hereinafter “Defendant Company”) that was the owner of a temporary building listed in the attached list (hereinafter “instant building”) agreed to transfer all rights to the said building to Defendant C.
On July 26, 2018, Defendant C agreed to transfer all rights to the said building to the Plaintiff.
B. As to the instant building, the Defendant Company: (a) performed the procedure for change of the owner’s name based on the transfer on June 5, 2002 to Defendant C; and (b) Defendant C is obligated to perform the procedure for change of the owner’s name based on the transfer on July 26, 2018 to the Plaintiff.
(2) Articles 257(1) and 208(3)1 of the Civil Procedure Act of the applicable provisions of Acts (Supreme Court Decision 208(3)1 of the Civil Procedure Act)