(영문) 수원지방법원 2019.09.26 2019가단543560
공사대금
Text

1. The defendant shall pay 60,879,900 won to the plaintiff and 12% per annum from June 18, 2019 to the day of complete payment.

Reasons

1. Indication of claims: To be as shown in the grounds for claims in attached Form;

(A) A creditor shall pay 67,879,900 won to the Plaintiff on February 1, 2018, as the tax invoice of 55,407,000 won and the tax invoice of 12,274,900 won on May 31, 2018, a creditor shall make and deliver to the Plaintiff a plan to pay the said amount in installments three times from October 31, 2018 to December 30, 2018, and the Defendant shall make and deliver to the Plaintiff a plan to pay the said amount in installments on June 27, 2018.

2. Grounds for recognition: Evidence Nos. 1 through 3 and the purport of the whole pleadings (the defendant was duly served and did not appear at the court);

3. Damages for delay: The amended provisions apply - The statutory interest rate prescribed by Presidential Decree, which was amended by Presidential Decree No. 29768 on May 21, 2019, which was enforced from June 1, 2019, pursuant to the main sentence of Article 3(1) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings, Etc., the term "interest rate prescribed by Presidential Decree" in the main sentence of Article 3(1) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings means 12/100 per annum. Thus, the damages for delay claimed by the Plaintiff in this case shall be applied to the Defendant from June 18, 2019, which was the day following the delivery of the original copy of the instant payment order.