(영문) 서울중앙지방법원 2015.06.12 2012가합106732
손해배상
Text

1. Defendant Korea’s 548,156,095 won and Plaintiff’s Compact global.

Reasons

1. Basic facts

A. The conclusion of the instant construction contract, etc. 1) Defendant Seoul Metropolitan Government, as part of the project for the specialization of the Han River zone around 2007, manufactures artificial trees using Han River water in the Gangseo-gu Seoul Metropolitan Government, the Han River-dong, the Han River-dong, the Han River-dong, and installs a marina and yacht and the main transportation, etc. that can pass by the marina and the Han River-dong vessel (hereinafter “instant project”).

(2) The Defendant Seoul Metropolitan Government planned the instant construction contract to implement a three-dimensional construction project to change the Olympic Games via the Han River District to underground passage (hereinafter “instant construction project”). The Defendant Seoul Metropolitan Government requested the Public Procurement Service affiliated with the Defendant Republic of Korea to conclude the instant construction project, and the Public Procurement Service announced the instant construction project announcement on June 2009 with the following contents:

For the end-user institution: The name of the Seoul Urban Infrastructure Headquarters of Seoul Special Metropolitan City for the construction site as the Olympic Games: the construction site as the Olympic Winter Games of Gangseo-gu Seoul Special Metropolitan City: the construction period as of 1,156 days from the date of commencement - the design period of 1,156 days from the date of commencement - the basic design and the design for preferential construction: 90 days from the date of the on-site explanation: the estimated amount of 120 days from the date of notification of the selection of the person qualified for the design: 181,324,00,000 won (the estimated price of 164,840,000,000 won as the estimated price of KRW 16,484,00,000,000 for value-added tax of 16,484,000 per day) shall be organized by a joint supply and demand organization of the plaintiffs (the investment ratio is

) The bid amount was KRW 129,100,00,000 (direct construction costs of KRW 90,029,957,220, indirect construction cost of KRW 13,92,51,028, general management cost of KRW 3,640,787,788, profit of KRW 4,639,034,912, construction damage insurance premium of KRW 550,00,000, design cost of KRW 80,000,000, design cost of KRW 4,340,123,416, and value-added tax on the total amount of KRW 4, 209) and participated in the bid procedure thereafter.