(영문) 전주지방법원남원지원 2015.09.03 2014가합367
공사대금 등
Text

1. The Plaintiff:

A. Defendant C’s KRW 97,966,709 as well as 5% per annum from November 15, 2014 to September 3, 2015.

Reasons

(c) Results of entrustment of appraisal (including results of supplementation of appraisal) to appraiser E, and the purport of whole pleadings;

2. Claim against Defendant C

A. 1) Claim for return of advance payment of KRW 11,492,21 remaining after deducting KRW 122,79 from KRW 234,00,00 paid by the Plaintiff from KRW 230,00,00, KRW 1200, KRW 122,50, KRW 221. 2) The Defendant C’s flag and calculation method: 29,99,352: The amount calculated by multiplying the remainder other than the above additional construction cost by the agreed price, 245,298,878: KRW 275,298, KRW 309, KRW 307, KRW 479, KRW 4797, KRW 4797, KRW 19747, KRW 4797, KRW 497, KRW 4797, KRW 297, KRW 197, KRW 3097, KRW 4797, KRW 297, KRW 4797, KRW 47947947.

B. 1) The Defendant C is liable for compensation to the Plaintiff, inasmuch as the overall purport of this Court’s appraisal result with respect to appraiser E is recognized as follows: (i) the amount of money classified by the sequence (unit: unit: 6,066, 2713, total sum of 141,3134, total sum of 15,8555 pented floor, 115,8455 pented floor, 66,03777, 27777, 198, 14. The Defendant C is liable to compensate the Plaintiff for the following. The amount of money classified by the sequence (unit: 6,066,4182, 156,2713, total sum of 141,3134, total sum of 1,485 pented floor of the first floor, 14,8455 pented floor of the instant construction, 2,037 pented concrete 2,1981.