logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 춘천지방법원강릉지원 2016.09.27 2015가합5555
공사대금
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. The Plaintiff (which is a person with the function of repairing cultural heritage as prescribed by the Act on Cultural Heritage Maintenance, Etc.) lent a construction business license from Daeyang-gu Co., Ltd. to construct the International Prior Experience Center (the first floor, the second floor, consisting of concrete cafeteria of a size of 160 square meters, the second floor, and the second floor, the 80 square meters, and the second floor) under the name of Taeyang-gu, Incheon, Incheon, under the name of Daeyang-gu, Inc., Ltd., (hereinafter “instant New Construction Project”) with a construction work newly constructed (hereinafter “the construction work of this case”), the construction cost of which is 66,66,00 won (including value-added tax), the construction period of which is fixed from August 1, 2009 to January 27, 2010, the construction cost of which is 1,63,340,000 won (including value-added tax) around September 20, 2010; and received the construction period from July 1010, 2010

B. Around April 2013, the Plaintiff submitted to the Defendant a detailed statement of additional construction cost of KRW 758,00,000, along with the attached Form D additional construction work cluster and other E and F additional construction work cluster, etc. Around that time, the Defendant issued and delivered a written claim for each of the above construction works (A evidence No. 14; hereinafter “instant written confirmation”).

C. On June 16, 2013, the Plaintiff drafted a document (Evidence A No. 13, hereinafter “instant written agreement”) with the Defendant as the title of the written agreement and signed between the Defendant, and the following is stated in the instant written agreement:

- The building Nos. 4 and 5 will be undertaken within the subcontracted part of the company that wants to have had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had had

· For additional construction costs, the amount recognized by the design office shall be settled.

- P.S. 1 E (2) G (3) Experience Center civil engineering.

arrow