(영문) 수원지방법원 2019.01.30 2018가단11011
건물명도
Text

1. The defendant shall give order to the plaintiff each point of indication 1, 2, 3, 4, and 1 of the annexed drawings among the second floor of the real estate listed in the annexed list.

Reasons

1. The Plaintiff with the indication of the claim is executing the redevelopment project for the housing redevelopment project for Suwon-si, Suwon-si, and the Defendant leased and occupied the building as stated in paragraph (1) of the disposition located in the project implementation district.

On December 31, 2015, the Plaintiff obtained authorization for the implementation of the project on December 31, 2015 from the Suwon City, obtained authorization for the management and disposal plan on August 2, 2017, and publicly announced the approved management and disposal plan.

Therefore, the defendant is obligated to deliver the above building to the plaintiff pursuant to Article 81 (1) of the Act on the Maintenance of Urban and Residential Environments.

2. Judgment made by the confession of applicable provisions of Acts (Article 208 (3) 2 of the Civil Procedure Act);