logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 의정부지방법원 2017.06.01 2016가단34229
건물명도
Text

1. The defendant

A. Of the real estate listed in the separate sheet, each point in the separate sheet Nos. 1, 2, 3, 4, and 1 shall be in sequence.

Reasons

1. According to the overall purport of Gap evidence Nos. 1 through 5 (including serial numbers) as to the cause of the claim, the plaintiff entered into a contract between the defendant and the defendant on April 24, 2014, on the following grounds: (a) as to the portion of "A" (hereinafter referred to as "the real estate in this case"), 300,000 won, monthly rent, 40,000 won, and from April 24, 2014 to April 23, 2016, the plaintiff delivered to the defendant a certificate of intention to lease the real estate in this case (hereinafter referred to as "the lease contract in this case") on the following grounds: (b) on the following grounds: (c) on the real estate listed in the separate sheet, the plaintiff did not deliver the real estate in this case to the defendant until October 23, 2016; and (d) on the grounds that the letter of intention to transfer the lease contract in this case to the defendant for late 205,006.

According to the above facts, the defendant did not pay the monthly rent for at least two months under the lease agreement of this case, and the lease contract of this case was lawfully terminated by service of content-certified mail.

Therefore, the Defendant is obligated to deliver the instant real estate to the Plaintiff and pay to the Plaintiff the remaining KRW 2,80,000,000, which remains after deducting the deposit amount of KRW 3 million from the overdue rent of KRW 5,280,000, and the amount calculated at the rate of KRW 440,000 per month from October 24, 2016 to the completion date of delivery of the instant real estate.

2. The conclusion is that the plaintiff's claim of this case is reasonable, and it is so decided as per Disposition.

arrow