(영문) 서울동부지방법원 2016.12.09 2016가단32415
물품대금
Text

1. The Defendant shall pay to the Plaintiff KRW 41,157,920 and the interest rate of KRW 15% per annum from September 10, 2016 to the day of complete payment.

Reasons

Comprehensively taking account of the respective descriptions and arguments in Gap 1-1-25, 2-1-25, 2-1-2-3, and 3-5, the Plaintiff sold products equivalent to KRW 41,157,920 ( KRW 100,774,700 - KRW 80,462,00 - 13,154,780) to Eul Co., Ltd. (hereinafter referred to as "foreign Co., Ltd.") from June 22, 2010 to November 19, 2014; and the fact that the Defendant, the representative director of the non-party Co., Ltd., was jointly and severally and severally liable to the Plaintiff on March 2016.

According to the above facts of recognition, the defendant is obligated to pay to the plaintiff 41,157,920 won for the above goods and damages for delay calculated at the rate of 15% per annum from September 10, 2016 to the date of full payment, as requested by the plaintiff, following the delivery date of a copy of the complaint in this case.

If so, the plaintiff's claim is justified.