(영문) 서울중앙지방법원 2018.10.11 2018가합519927
매매대금
Text

1. The defendant shall be the plaintiff.

(a) KRW 154,00,000 as well as 6% per annum from March 29, 2018 to July 30, 2018; and

Reasons

1. Basic facts

A. The Plaintiff is a company that runs the manufacturing business and wholesale and retail business of construction and industrial machinery, etc., and the Defendant is a person who runs a wholesale and retail business of waste electric wires.

B. On October 19, 2017, the Plaintiff entered into a contract with the Defendant to sell scrap metal and used goods stored in a factory located in 107-5, 107-5, Yon-ro, Yon-ro, Yon-ro, Yon-ro, Yon-gun, Yon-nam Budget-gun (hereinafter “factory operation”) (hereinafter “the instant sales contract”) within the scope of 177, Yon-ro, Yon-nam, Yon-nam Budget-gun, and the main contents are as follows.

Article 1 (Goods subject to Sale) The scrap metal and used goods (hereinafter referred to as "goods") that the plaintiff trades to the defendant pursuant to the instant sales contract shall be as follows, and the details thereof shall be as follows:

Article 3 (Sale Price) (1) No later than December 30, 2017, Article 3 (Sale Price for Used Goods, other than 1770t halog halog halog haul haul haul gale, etc., from the 107-5 Gaon-ro, Go-dong, Go-dong, Daon-dong, Chungcheongnam-dong, Chungcheongnam-dong, the factory, Chungcheongnam-dong, Seoul Metropolitan Government, by November 30, 2017, the sales price of the goods shall be determined as KRW 850,00,00 (excluding value-added tax) and the defendant shall pay the amount to the plaintiff in accordance with the following conditions:

Article 5 (Delivery of Goods) (1) of the remainder of October 19, 2017 on October 31, 2017: (a) The Plaintiff shall immediately complete the preparation for delivery of the goods and ensure that the instant sales contract can be smoothly implemented upon the completion of the preparation for delivery of the goods immediately after the Defendant pays any balance of the purchase price.

② The Defendant shall take out all the goods within the period specified in Article 1 of the instant sales contract.

Article 13 (Matters of Special Agreement) (2) Where the defendant exceeds the shipment period of goods stored in the bonded area, an amount equivalent to 2,000,000 won/months (excluding value-added tax) shall be paid monthly to the plaintiff.

C. After that, the Plaintiff and the Defendant concluded several contracts of this case.