Defendants jointly and severally liable to the Plaintiff for KRW 511,050,810 and KRW 509,189,040 from May 10, 201 to December 5, 2015.
Reasons
Description of Claim
Attached Form
same as the reasons for the claim.
The part rejecting part of Article 208 (3) 3 of the Civil Procedure Act of the applicable provisions of the Acts refers to a claim for damages for delay at the rate of 20% per annum from the day following the date of last delivery of the copy of the complaint of this case. However, since the statutory interest rate was changed to 15% per annum pursuant to the main sentence of Article 3 (1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings amended by Presidential Decree No. 26553 on September 25, 2015, the part claiming damages for delay calculated at the rate exceeding 15% per annum among the plaintiff's claims for damages for delay