(영문) 부산고등법원 2019.08.28 2018나58250
사용료 등
Text

1. The defendant's appeal is dismissed.

2. The costs of appeal shall be borne by the Defendant.

Purport of claim and appeal

1..

Reasons

. For the materials damaged or destroyed after use, the cost of loss shall be paid to the Plaintiff in accordance with the loss cost schedule.

(j) Extension of the lease period: The defendant shall return the whole rental materials at the time of completion of the lease period except for the suspension of construction due to a natural disaster, and shall pay daily rent to the plaintiff when it is inevitable to extend the lease period, and the daily rent shall correspond to the unit price table of the general household.

손망실단가표 품명 규격 가격(원) 비고 품명 규격 가격(원) 비고 유로폼 6012 17,000 고재 써포트 V2 13,000 6012 36,500 신재 V4 15,000 5012 17,000 고재 V5 19,000 5012 26,000 신재 V6 21,000 4512 15,000 고재 파이프 6M 16,000 4512 22,000 신재 4M 12,000 4012 15,000 고재 3M 8,000 4012 21,000 신재 2M 5,500 3512 16,000 고재 인코너 100*100 11,000 고재 3512 20,000 신재 100*100 14,000 신재 3012 15,000 고재 100*150 12,000 고재 3012 18,000 신재 100*150 15,000 신재 2012 12,000 고재 100*200 13,000 고재 2012 15,000 신재 100*200 16,000 신재 O/C 앵글 2.4M 16,000 150*150 13,000 고재 1.2M 8,000 150*150 16,000 신재 B/T아시바 1셋트 80,000 각파이프 4M 12,000 안전발판 400*182P 15,000 고재 3M 9,000 400*182P 20,000 신재 2M 6,000 2) 이 사건 임대차계약서에는 손망실단가표가 첨부되어 있는데, 그 내용은 다음과 같다. 라. 이 사건 임대차계약에 의한 원고의 가설재 공급 및 피고의 가설재 반환 등 1) F동 공사현장에 대한 공급 및 반환 가) 원고는 2016. 6. 25.부터 이 사건 임대차계약의 임대기간 종료 전인 2016. 9. 28.경까지 F동 공사현장에 투바이, 유로폼, 인코너 등 가설재 18,223개를 공급하는 한편, 임대기간이 종료된 후인 2016. 10. 17.경부터 2017. 8. 1.경까지에도 F동 공사현장에 사각파이프, 유로폼(B급) 등 가설재 5,389개를 공급하여 총 23,612개(=18,223개 5,389개)의 가설재를 공급하였다. 나) 피고는...