(영문) 수원지방법원안산지원 2019.09.20 2019가단61208
건물명도(인도)
Text

1. Defendant B Co., Ltd.:

(a) deliver a factory of 489 square meters among the 1st floor of the building listed in the attached list;

(b) 29.

Reasons

1. Indication of claims: It shall be as shown in attached Form; and

2. Judgment by deeming confession (Article 208(3)2 and Article 150(3) of the Civil Procedure Act, and Article 208(3)2 and Article 150(3) of the same Act, and Article 150(3) of the same Act, even though the Defendant Company submitted a written reply, the purport of disputing the Plaintiff’s claim was not included in the written reply, and thus, the Plaintiff

3. As the provisions on statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases concerning Expedition, etc. of Legal Proceedings for Partial Dismissal were promulgated on May 21, 2019 and enforced from June 1, 2019, the statutory interest rate was 12% per annum from June 1, 2019, it is recognized only as damages for delay calculated at the rate of 12% per annum from June 1, 2019, and the exceeding part of the claim is dismissed.