1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
1. Facts of recognition;
A. On November 2, 2013, the Plaintiff entered into a design service contract with the original Defendant (i) and (ii) around November 2, 2013, the 1st floor building and the 1st floor building on the 3rd floor and the 2nd floor building on the 3rd floor at Kim Jong-si (hereinafter “instant building”).
(2) On January 16, 2014, the Defendant, who represented by the Plaintiff, filed an application for permission to construct (extension for the purpose of extension and large-scale repair) the instant building at the time of Kim Jong-do, and obtained permission from Kim Jong-si on February 28, 2014.
B. On April 22, 2014, the Plaintiff entered into the instant first contract with the Defendant and the Plaintiff for the extension, alteration of the purpose of use, and large-scale repair of the instant building (hereinafter “instant construction”).
) The contract under which the contract is made (hereinafter referred to as “instant contract”).
(A) the standard contract for private construction works (hereinafter referred to as “instant contract”) at the time of signing the contract.
2) The instant contract document contains the following descriptions:
Construction name: The date scheduled for the commencement of construction works for the extension, alteration of the purpose of use, large-scale repair: The date scheduled for the completion of April 2014: September 30, 2014 seems to be written in writing.
Contract amount: 1.350 million won (excluding value-added tax): 100 million won: Other matters may be changed at the time of changing design and construction period. Defendant 3) commenced the instant construction work around May 10, 2015. (C) The Plaintiff requested the Defendant to design the construction of the instant building on July 2014, and the Defendant received the construction permission from Kim Jong-si on September 24, 2014 after filing an application for the construction permission for the extension of the fourth floor of the instant building on September 5, 2014.
2) On September 25, 2014, the Plaintiff and the Defendant and the contractor “contractor rink Construction Co., Ltd. (which was changed to a sunken road Construction Co., Ltd.; hereinafter referred to as “K Construction”).
....