Text
1. The plaintiffs' main claim part of each real estate listed in the plaintiffs' list shall be dismissed.
2. Defendant.
Reasons
1. Summary of the plaintiffs' assertion
A. The relationship between the parties (1) The defendant company is a company engaged in building business, and the plaintiffs are those who subcontracted a part of the construction work from the defendant company and performed the construction work, and the defendant J is the spouse of L who is the representative director of the defendant company, and the defendant K is the same as the above L company's auditor.
② On May 12, 2010, Defendant H entered into a contract for construction works with the Defendant Company with respect to the construction of a new apartment house on the land outside M and five parcels (hereinafter “instant construction works”).
B. The Plaintiffs’ claim for the construction price against the Defendant Company (hereinafter “Plaintiff A”) holds against the Defendant Company the unpaid construction price equivalent to KRW 75 million and damages for delay.
② The Plaintiff Company completed the construction by entering into a subcontract with the Defendant Company for the construction of the main household and the new studs among the construction works for re-building on the land of Yangcheon-gu Seoul N and five parcels (hereinafter “instant Nre-building works”). The Defendant Company is obligated to pay the Plaintiff B the construction cost of KRW 10,80,000 and the damages for delay.
③ The Plaintiff Co., Ltd. completed the construction work by subcontracting the construction work from the Defendant Co., Ltd. among the N-building work in this case. The Defendant Co., Ltd is obligated to pay the Plaintiff Co. for the construction cost of eight million won and delay damages.
④ The Plaintiff D applied for a payment order against the Defendant Company after receiving a subcontract for interior decoration among the N reconstruction Works in this case from the Defendant Company, and completing the construction work, and upon receiving a final payment order against the Defendant Company, the Defendant Company has a claim for KRW 31,283,00 and damages for delay.
⑤ The Plaintiff E subcontracted the instant N-building work from the Defendant Company to complete the said work. The Defendant Company is the Plaintiff.