(영문) 서울중앙지방법원 2015.06.11 2013가합31699
구상금 등
Text

1. The plaintiff's claim is dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On November 25, 2009, the Plaintiff entered into an agreement, etc. related to multi-family housing business (i.e., multi-family housing business) and changed from the Defendant (Defendant Co., Ltd.) to the present trade name.

(1) or a third party corporation (hereinafter referred to as “third party corporation”) in which the Defendant owns shares.

In addition, there seems to be a lot number of 1510, Ansan-gu, Asan-dong, Pasan-dong, following the implementation of the project for the land of the 86 to 88 block from the Korea Water Resources Corporation (hereinafter referred to as the “instant land”).

(2) The business of constructing and selling the apartment on the ground of the purchase in lots (hereinafter referred to as the “instant business”).

2) On October 17, 2001, the Plaintiff jointly promoted the agreement with the Defendant and the Defendant on November 9, 2001 (hereinafter the above agreement, each of the “instant agreement,” and the “instant agreement,” respectively, signed on October 9, 2001, and the main contents related to the instant case are as follows.

[This Convention] To promote a housing construction project with respect to the land of this case sold by the Korea Water Resources Corporation and to enter into an agreement as follows, and to establish two copies of this agreement and keep one copy of each agreement after signing and sealing the agreement.

Article 3 (Basic Principle of Implementation of Joint Projects) The three-day industry and the basic matters to be carried out by the plaintiff shall be as follows:

1. The primary spirit is to bear 50% of the input costs for the project and to recover business profits by 50%.

3.The three-day business shall be the joint project undertakers (joint implementers) of this project and shall be responsible for the obligations of the three-day business as provided for in this Convention.

4. The plaintiff is a joint project proprietor and a joint project executor who is concurrently a joint project executor and carries out this project, and the plaintiff's obligations as stipulated in this Convention are fulfilled.