1. The Defendant’s KRW 90,000,000 as well as 8.5% per annum from May 30, 2014 to June 30, 2014 to the Plaintiff.

Reasons

1. Facts constituting the cause of claim;

A. On December 30, 2013, the Plaintiff lent KRW 500,000 to the non-party East Development Co., Ltd. at the interest rate of 8.5% per annum on June 30, 2014 (the annual overdue interest rate of 11.5% per annum for at least one month, plus the agreed interest rate). On June 30, 2014, the Defendant set the ceiling amount of the obligation to return the loan at KRW 650,000,000,000.

B. Since May 30, 2014, Dong Dong Development Co., Ltd. has not repaid the principal and interest of the above loans.

[Evidence: Facts without dispute; evidence No. 1-3; evidence No. 2 and 3; purport of the whole pleadings]

2. Therefore, the Defendant, as a part of the above loans, is obligated to pay the Plaintiff the principal of KRW 90,000,000 and interest and delay damages calculated at the rate of 8.5% per annum from May 30, 2014 to June 30, 2014, and 20% per annum from the next day to the date of full payment, as the Plaintiff seeks.