(영문) 제주지방법원 2021.02.19 2019가합11216
공사대금
Text

1. The Defendant’s KRW 90,921,950 as well as the Plaintiff’s annual rate of 6% from June 1, 2014 to December 7, 2017.

Reasons

1. Basic facts

A. The Plaintiff is a corporation that is engaged in civil engineering works, construction works, etc.

2) The Defendant is an incorporated foundation established to maintain and manage B’s property, which is a religious organization, and C’s agricultural partnership (hereinafter “C partnership”) is a corporation established under the Act on Fostering and Supporting Agricultural and Fishing Enterprises.

3) D is the chairperson of the E Promotion Committee established by the former representative director of C Union from May 30, 2012 to December 8, 2014 after resignation from May 30, 2012 established by C Union and completing the registration of resignation on December 9, 2014.

B. On December 28, 2011, D concluded, as the Defendant’s representative, a contract with the Plaintiff, setting the contract amount of KRW 9,600,00,000 for construction of a religious facility consisting of two Dongs in E (No. s. 1/100,00 among the religious facilities of this case), education centers, and care centers for the aged and children’s facilities (hereinafter “the instant elderly facilities”) on the ground of two parcels of land, other than F in Jeju-si, the Defendant owned by the Plaintiff (hereinafter “the instant religious facility”). The contract was concluded between the Plaintiff and the Plaintiff on the terms that the construction works are to be built on the instant elderly facilities of this case (hereinafter “the instant elderly facilities”) at a fixed rate of KRW 9,60,00,00 ( separate value added tax), June 30, 2014; and the expected date of completion of construction (hereinafter “the first contract”).

2) On January 5, 2012, the Defendant obtained a building permit from the Jeju Mayor for the construction of the instant religious facilities and the instant facilities for the elderly, and obtained a building permit for the construction of the instant religious facilities from the Jeju Mayor by modifying the said permit on June 5, 2012.

(c)

1) Around June 2013, D agreed that the Defendant and C shall divide the primary contract into two parts and make part of the contract each with the Plaintiff, and that the total contract amount shall be KRW 1,000,000,000, which was already paid under the primary contract, shall be KRW 8,600,000,000 (excluding value added tax).

2) Accordingly, D around that time is the representative of the defendant, G orchard in Jeju.