Text
1. The Defendant’s KRW 50,000,000 and the Plaintiff’s annual rate of 5% from October 25, 2017 to September 19, 2019.
Reasons
1. Claim for each loan of KRW 30 million as of September 26, 2017, KRW 50 million as of October 10, 2017, and KRW 10 million as of October 24, 2017, respectively;
2. Judgment without holding any pleadings: Articles 208 (3) 1 and 257 of the Civil Procedure Act;
3. The part to which partial dismissal is dismissed is claimed for the payment of damages for delay calculated at the rate of 12% per annum from October 25, 2017 to the date of full payment. However, there is no assertion as to the agreement on the interest rate, and therefore, the part to which the Civil Act does not apply until the delivery date of a copy of the complaint of this case exceeds the rate of 5% per annum as stipulated in the Civil Act.