(영문) 울산지방법원 2018.08.29 2016가합21786
손해배상(기)
Text

1. The Defendants shall jointly and severally serve as the Plaintiff the amount of KRW 108,340,842, and as a result, from June 21, 2016 to August 29, 2018.

Reasons

(b) the facts of the basis;

A. On June 22, 2015, the Plaintiff was awarded a contract with D for the new construction of Jeju Special Self-Governing Province E and two parcels on the ground (hereinafter “instant new construction project”).

B. On July 1, 2015, the Plaintiff entered into a subcontract (hereinafter “instant contract”) with respect to construction works among the instant new construction works (hereinafter “construction works”) with Defendant B as its representative, and the main contents are as follows.

Standard subcontract form of construction works

1. Project owner: D - Original Contract Name: New construction works of Jeju-do;

2. The name of the subcontracted project: Construction work among the new construction work of Jeju-do.

3. Construction site: Two parcels, including E, in Jeju Special Self-Governing Province.

4. Construction period: The contract amount from July 1, 2015 to March 20, 2016: The daily twenty-one hundred billion won (Won 2,310,000,000): The daily twenty-one hundred million won (Won 2,100,000), the daily twenty-one hundred-one hundred-one hundred-one hundred-one million won (one-one labor expense): The value-added tax on labor expenses under Article 84 of the Enforcement Decree of the Framework Act on the Construction Industry* The daily twenty-one hundred-one hundred-one hundred-one (Won 210,00,000).

6. Payment of the price:

(a) Down payment: 7/6,55,000,000 (vat);

(b) The completed amount: the application of the monthly fairness rate; and

(c) Completion money: 500 million won (Vat rating) shall be adjusted following the completion of a building, the adjustment of the price and payment following a change in the conditions that the bank will pay after registration: it shall be adjusted in consultation with each other at the

7. Scope of construction: Construction conducted based on a drawing and estimate; and

8. Contract bond: 10%;

9. Warranty bond rate: 5% 10% : 0.3% : 12% : Other matters including water tank construction (construction after consultation on civil construction): Article 18 (Adjustment of Contract Price due to Modification of Design) 18 (Adjustment of Contract Amount due to Modification of Design) (1) Any situation in which the contents of the design do not coincide with the state of the construction site, or are unclear, omitted or erroneous, or unexpected in relation to construction, or any modification of the project plan, etc.