logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2020.12.09 2018가합518979
손해배상(기)
Text

1. The plaintiff's claims against the defendants are all dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

(b)in the NAB method;

[3] Paragraphs (3) and (4) omitted) Article 3 (Production Costs) 1) of the App 3 (Production Costs) 1) the total cost of the instant app 140,000,000 won per day (excluding value-added tax). A. D. simultaneously with the contract, the Plaintiff pays 35,00,000 won (excluding value-added tax) equivalent to 25% of the total cost of the manufacture as stipulated in paragraph (1) above, to D as down payment.

(b) part payments: the Plaintiff shall pay to D the amount equivalent to 10% of the total production costs under the above paragraph (1) above out of the total production costs under the above paragraph (1) at the primary cost, and shall pay to D the amount equivalent to 10% of the total production cost at the secondary cost when the total production cost is in progress at 30%, and shall pay to D the amount equivalent to 15% of the total production cost at the third cost when the total production cost is in progress at 50% of the total production cost. This is as follows. The amount shall be paid to D at the third cost. The payment rate of the total production cost (excluding value-added tax) at the rate of 10% 14%,00,000, 100% 14,000%, 100%, 100%, 201, 200%, 100%, 200%, 100%, 000 of the intermediate payment condition*

C. Balance: The Plaintiff will pay to D any balance of KRW 56,00,000 (value added tax) when completing the manufacture of the app from D.

app manufacturing completion date means the date D, with the consent of the plaintiff, shall be the date on which D registers this app in the Stop.

2) In providing the terms provided for in Article 2, additional production costs may be claimed for a separate work not indicated in the contract. Article 4 (Period of Contract) (1) The period of this Agreement shall be from 10 June 2015 to 21 August 2015.

2) D must complete the app requested by the Plaintiff by the date of maturity of the said contract, and D shall compensate the Plaintiff without objection, for the delayed delay multiplied by 3/1,000 of the total cost of production as set forth in Article 3(1) per day without delay as of the banking business day.

3) In a case where D completed the app and registered at the Plaintiff’s request after the date of the said contract, the Plaintiff deducted the amount corresponding to paragraph 2(2) from the balance of D.

arrow