Text
1. The Defendants jointly and severally pay to the Plaintiff KRW 325,198,102 as well as KRW 87,698,597 as well as the full payment from May 9, 2016.
Reasons
In full view of the overall purport of the arguments in Gap evidence Nos. 1 through 8, the fact that the reasons for the application are stated in the attached Form (However, the creditor is considered as the plaintiff, and the debtor is considered as the defendant) can be recognized.
Therefore, the Defendants jointly and severally pay to the Plaintiff damages for delay calculated at the rate of 24% per annum from May 9, 2016 to the date following the date of final calculation of interest for the total amount of KRW 325,198,102 and the principal of the loan, which is the sum of the principal and interest of KRW 87,698,597, and the total amount of the loan, and Defendant B is obligated to pay the above amount within the limit of KRW 625,00,000 in total.
The plaintiff's claim against the defendant A is justified and accepted. The claim against the defendant B is justified within the scope of the above recognition, and the remaining claim is dismissed as it is without merit. It is so decided as per Disposition.