(영문) 의정부지방법원고양지원 2019.08.28 2019가단4338
공사대금
Text

1. The Defendant’s KRW 70 million with respect to the Plaintiff and 5% per annum from July 1, 2016 to July 3, 2019.

Reasons

1. Indication of claims: It shall be as shown in attached Form; and

2. Judgment by service (Article 208 (3) 3 of the Civil Procedure Act).

3. Partial dismissal: The provisions pertaining to statutory interest rates under the main sentence of Article 3(1) of the Act on Special Cases concerning Expedition, etc. of Legal Proceedings (hereinafter “Promotion Act”) were promulgated on May 21, 2019 and enforced from June 1, 2019. Since the statutory interest rate under the Promotion Act was 12% per annum from June 1, 2019, the damages for delay from July 4, 2019 recognized as 12% per annum, and the exceeding part is dismissed.