(영문) 서울동부지방법원 2016.07.22 2016가단114812
양수금
Text

1. The defendant shall pay KRW 27,217,308 to the plaintiff.

2. The costs of the lawsuit are assessed against the defendant.

3.Paragraph 1.

Reasons

Comprehensively taking account of the respective descriptions and arguments set forth in Gap 1-4, the Songpo Agricultural Cooperative may recognize the fact that on September 13, 2010, the defendant transferred KRW 170 million to the defendant on September 13, 2012, the due date for payment, KRW 0.45% of the interest rate, KRW 0.45% of the overdue interest rate, and KRW 6% of the loan interest rate if the overdue interest rate is less than one month but less than three months, and KRW 7% of the loan interest rate if the overdue interest rate is more than one month and less than three months, and KRW 9% of the loan interest rate if the above loans are more than three months, the defendant failed to repay the total amount of KRW 27,217,308 of the interest and delay damages, etc. among the above loans, and the Songpo Agricultural Cooperative transferred KRW 27,217,308 to the plaintiff on August 27, 2014, and notified the defendant of the transfer of

According to the above facts of recognition, the defendant is obligated to pay KRW 27,217,308 to the plaintiff. Thus, the plaintiff's claim is accepted for reasons.

arrow