(영문) 대전지방법원 2015.03.05 2014가단211753
공사대금
Text

1. The Defendant shall pay 21,700,800 won to the Plaintiff and 20% per annum from June 3, 2014 to the day of complete payment.

Reasons

1. Facts of recognition;

A. The Plaintiff entered into a contract with the Defendant for the execution of the customer’s burden of connection facilities for transmission at the YO Headquarters (hereinafter collectively referred to as the “instant contract”) in accordance with the rules on the use of electrical facilities for transmission only as listed below.

Serial 1: The contract amount of the construction period (Additional Tax No. 1; 345km) on the date of the construction order contract (Additional Tax No. 1: 345km, May 19, 201; 200 won from May 24, 2011 to May 27, 2011; 9,983,000 won 2: 1; 2.6.36.6.6.6.6.7.5.20 to June 20, 2012; 206.4.6.6.4.6.6.6.6.3.6.6.6,640; 141.79; 793; 3.6.45.6.6.4.6.6.25.6.6.6.201.

B. At the time of the conclusion of the instant contract, the “construction cost for connection facilities for transmission” shall be calculated as the design amount according to the Plaintiff’s design standards and accounting regulations, and the determination of construction cost shall be determined at the time of settlement after the completion of the construction, and shall also be deemed to include the Plaintiff’s own implementation design and construction supervision cost (self-design cost

C. After the completion of construction, the Plaintiff settled the cost of construction with the Defendant and received all the amount indicated in the column for the settlement amount of the said Table from the Defendant.

However, around September 2013, the Plaintiff pointed out that, as a result of internal audit conducted by the Daejeon District Headquarters, the Plaintiff had to add up general management expenses, etc. for private supply materials directly purchased by the Plaintiff for construction, while calculating the cost of customer burden. However, the Plaintiff requested corrective measures.

E. Accordingly, the Cheongyang Military Manpower Center affiliated with the Plaintiff is the Daejeon Military Manpower Center.