(영문) 서울중앙지방법원 2018. 1. 18. 선고 2017가합18540 제31민사부 판결
대여금
Cases

2017 Gohap18540 Loans

Plaintiff

Design Group architect, Inc.

Defendant

1. A regional housing association;

2. B

Conclusion of Pleadings

December 8, 2017

Imposition of Judgment

January 18, 2018

Text

1. The Defendants jointly and severally pay to the Plaintiff 300,000,000 won with 15% interest per annum from June 29, 2017 to the day of full payment.

2. The costs of lawsuit are assessed against the Defendants.

3. Paragraph 1 can be provisionally executed.

Purport of claim

The same shall apply to the order.

Reasons

1. Basic facts

On July 16, 2015, the Plaintiff agreed to lend KRW 300 million to Defendant A’s regional housing association and six months after receipt of the loan due, and deposited KRW 300 million in accordance with an agreement on July 24, 2015. Defendant B guaranteed the above loan obligations of Defendant A’s regional housing association.

[Grounds for Recognition] deemed confession (Article 150 (1) of the Civil Procedure Act)

2. Determination as to the cause of action

According to the above facts, the defendants are jointly and severally liable to pay delay damages calculated at the rate of 15% per annum from June 29, 2017 to the day of full payment, which is the day following the day when the copy of the complaint of this case was served on the defendants, to the day of full payment.

3. Conclusion

Therefore, the plaintiff's claim against the defendants shall be accepted for all reasons, and this decision is delivered with the disposition.