(영문) 광주지방법원 2016.06.08 2016가단8089
물품대금
Text

1. The Defendant’s KRW 96,925,00 for the Plaintiff and the following: 5% per annum from July 17, 2015 to February 15, 2016, respectively.

Reasons

1. The plaintiff is a business operator who sells freezing machinery, etc., and the defendant is a business operator who manufactures and sells synthetic resin, etc.

The Plaintiff supplied goods to the Defendant from February 13, 2015 to July 16, 2015, but the Defendant paid only KRW 28,200,000 on June 4, 2015.

The plaintiff claims for the payment of the unpaid amount of KRW 96,925,00 and damages for delay.

2. Article 208(3)2 of the Civil Procedure Act (the defendant only submitted a formal written objection with the original copy of the instant payment order, and did not reply to the plaintiff's assertion on the date of pleading, and since he did not appear on the date of pleading, it is deemed that all the plaintiff's assertion was led to a confession pursuant to Article 150 of the Civil Procedure Act).