Defendant shall be punished by a fine of KRW 2,000,000.
When the defendant does not pay the above fine, 100,000 won.
Reasons
Punishment of the crime
From April 2013 to July 18, 2014, the Defendant constructed a manager of 1, 98 square meters using a steel pipe and a balking mar, without obtaining permission from the competent authority, in Kimhae-si B, the development restriction zone, from around April 2013 to around July 18, 2014, and constructed one 52 square meters of a residential building to a prefabricated-type panel on the above internal manager, and sealed the said manager’s floor of 98 square meters as concrete.
Summary of Evidence
1. Statement by the defendant in court;
1. A written accusation and a statement supplementary to public officials;
1. Application of the current status of offenses, confirmation of land use plan, and land ledger-related Acts and subordinate statutes;
1. Relevant Article of the Act and Article 32 subparagraph 1 of the Act on Special Measures for Designation and Management of Areas subject to Restrictions on the Selective Development of Punishment and Punishment for Criminal Facts, and Article 12 subparagraph 1 (e) of the proviso to Article 12 (1) of the Act on Special Measures for Designation
1. Article 70(1) and Article 69(2) of the Criminal Act to attract a workhouse;
1. Article 334 (1) of the Criminal Procedure Act concerning the order of provisional payment;