Text
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
1. Basic facts
A. The Plaintiff is a corporation established for the purpose of general construction business, manufacturing steel products and steel products business, manufacturing and selling construction materials, etc.
B. (1) On November 4, 2015, the Plaintiff entered into a contract with multiple suppliers, etc. (hereinafter “instant goods”) with the Defendant and the tea separation zone manufactured by the Plaintiff (hereinafter “instant goods”).
() The term of contract of 30,000 items is from November 4, 2015 to September 30, 2017; the contract amount is 4,575,000,000 won; the contract deposit is 228,750,000 won; and the contract deposit is 228,750,000 won and is supplied at a place designated by each end-user institution pursuant to Article 7-2 of the Enforcement Decree of the Act on the Procurement of Goods Contracts, where it is deemed necessary to satisfy various needs of each end-user institution in purchasing commodities commonly used by each end-user institution, it refers to a contract system under which two or more parties are allowed to select items equal to or similar to quality efficiency, etc., if the multiple suppliers enter into a contract, and if each end-user institution requests the supply of items registered, the contract is implemented by changing the contract amount to the end-user institution at the request of the supply. The contract amount is 00,700,700,005,70000 each of this case.
hereinafter referred to as "the instant contract" is referred to as "the instant contract"
A.3.1 Materials A. B A. A. C.3.5 Ma and external appearance 1) is a form of a body formed in salary and beeas as a basic composition that solid installation on the ground by salary and V, installed on the surface of materials A. A. B A. C. C.3.5 Ma and appearance 1).