(영문) 울산지방법원 2016.03.11 2015가단20178
물품대금
Text

1. The Defendant’s KRW 60,559,950 for the Plaintiff and its related KRW 5% per annum from February 21, 2014 to September 21, 2015, and September 22, 2015.

Reasons

1. The description of the grounds for the claim shall be as specified in the attached Form;

(4) Article 208(3)1 of the Civil Procedure Act, and Article 257(1)1 of the Civil Procedure Act, a judgment without pleading is rendered on December 1, 201.

3. There is no proof of assertion as to an indemnity agreement for delay in the payment of the cost of goods. Thus, only damages for delay shall be recognized from the interest rate prescribed in the Civil Act until the delivery date of the duplicate of the complaint of this case. As the provisions on statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings were amended and promulgated on September 25, 2015 and enforced from October 1, 2015, the following day after the delivery date of the duplicate of the complaint of this case shall be 20% per annum from September 22, 2015 to September 30, 2015, and damages for delay shall be recognized from the next day to the day of full payment.