1. The defendant
A. 43,026,00 won to Plaintiff A and 5% per annum from November 23, 2011 to September 5, 2014.
Reasons
1. Under the facts, Plaintiff A was the owner of the land C 284m2 (hereinafter “C land”), the Plaintiff B was the owner of the said land prior to D 585m2 (hereinafter “D land”), and was the owner of the said two parcels of land (hereinafter “each of the instant land”).
In order to implement the F Road Packing Project, which is an urban planning project (hereinafter “instant road project”), pursuant to the Notification E in 1999, the Defendant acquired each of the instant land from the Plaintiffs as indicated in the “Real Estate Acquisition Details Table” as indicated in the following Table 1, in accordance with the former Act on Special Cases Concerning the Acquisition of Land for Public Use and the Compensation for Loss (repealed by Act No. 6656, Feb. 4, 2002; hereinafter the same) in order to implement the said road project (hereinafter “instant road project”), and completed the registration of ownership transfer in the future for each of the above land.
On November 15, 1999, 199. 51,830,002 Plaintiff C land on November 23, 1999, Plaintiff B D land on November 23, 1999, 199: (a) The Minister of Construction and Transportation announced G around April 25, 200 of the acquisition details list of real estate / The Minister of Construction and Transportation announced G as the J-si site development district including each of the instant land, and the H and I-Eup area as the J-si site development district; (b) on December 14, 2001, approved the alteration of the housing site development district and development plan for the instant land to K-si site development district and the alteration of the area of each of the instant land to the K-si site development plan (the Ministry of Construction and Transportation announced as the alteration of the area of each of the instant land to the K-si site development plan, and (c) on December 26, 2002.
The road project of this case to be implemented by the defendant is a route number M, route number N through O in the ethrified city, total extension of 3.34 km, width of 20 km (4 lanes), project implementation period from September 199 to December 30, 2004.