logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원성남지원 2019.05.29 2018가단19216
각서금
Text

1. As to the Plaintiff’s KRW 54,00,000 and KRW 27,000 among them, the Defendant shall start on November 11, 2017 and end on 27,000.

Reasons

In full view of the purport of the argument in Gap evidence No. 3, the defendant, on September 25, 2017, paid the construction price of KRW 54 million to the plaintiff on September 25, 2017; however, it can be acknowledged that the defendant agreed to pay KRW 27 million up to November 10, 2017, and the remainder KRW 27 million up to December 29, 2017.

Therefore, the defendant is obligated to pay to the plaintiff the above 54 million won and the remaining 27 million won from November 11, 2017 to December 30, 2017 to December 27, 2018, the amount of delay damages calculated at the rate of 5% per annum under the Civil Act and 15% per annum under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from the next day to the day of full payment. Thus, the plaintiff's claim of this case is justified within the above scope of recognition, and the plaintiff's remaining claim for delay damages (the plaintiff filed a claim for delay damages from September 26, 2017 to the whole amount of 54 million won). Thus, it is dismissed as per Disposition.

arrow