(영문) 대전지방법원 공주지원 2019.09.06 2019고단244
산업안전보건법위반
Text

1. Defendant A shall be punished by imprisonment for eight months.

However, for two years from the date this judgment becomes final and conclusive, the above sentence shall be executed.

Reasons

Punishment of the crime

Defendant

A is a person who is obligated to take safety and health measures for his/her employees as the site manager of the "D Repair Work" performed by the Defendant B Company, a business owner, in the official city of official city.

1. Defendant A

(a) A business owner involved in a serious accident at a place of business on May 25, 2018, when engaged in work using a vehicle gauge, shall place an guide and shall not allow workers to enter a place where workers are in contact with the relevant vehicle gauge and are at risk of putting workers on board, except in cases of inducing the relevant vehicle gauge to do so, and shall not cause workers' death in violation of this provision;

Nevertheless, at around 16:40 on May 25, 2018, the Defendant: (a) provided F with a vehicle stringer using a vehicle strawls, without any separate leading person on the two-lane E, and (b) provided G (50) with a vehicle stringer “stringer” at the same time between the first-lane and the second-lane, the Defendant led F to the death of a large truck approaching a two-lane by avoiding a large truck approachinging a two-lane depending on the first lane to the “Tring string string string string string string string string string string.”

B. A business owner related to the regular supervision of a workplace from May 26, 2018 to May 28, 2018 shall conduct a prior inspection of the geographical features, geographical features, geographical features, and geographical features of the workplace, etc. in order to prevent the danger of workers, and prepare a work plan in consideration of the results of the investigation, and conduct the work in accordance with the plan.

Nevertheless, the Defendant did not prepare a vehicle-based construction machinery work plan from May 26, 2018 to February 28 of the same month at the repair work site, and let F go off.