logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 부산지방법원동부지원 2017.07.14 2017가합376
물품대금
Text

1. The Defendant’s KRW 206,232,694 as well as 6% per annum from May 20, 2016 to May 4, 2017 to the Plaintiff.

Reasons

1. Indication of claim;

A. The Plaintiff is a person who engages in steel scraping and wholesale and retail business with the trade name of B, and the Defendant is a corporation established for the purpose of manufacturing ship structures.

From November 2007 to May 201, 2015, the Plaintiff supplied the Defendant with goods, such as 318,399,694 square pipes and flat iron.

B. The defendant paid only KRW 112,167,00 as the price for goods, and does not pay the remainder of the price for goods.

Accordingly, the plaintiff claims the amount of the unpaid goods and damages for delay.

2. Judgment without holding any pleadings (Articles 208 (3) 1 and 257 of the Civil Procedure Act);

arrow