Text
1. The plaintiff's claims against the defendants are all dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
1. Basic facts
A. The plaintiff is "the subject matter of auction of this case" in the separate list No. 2, and with respect to individual real estate, the plaintiff is "the subject matter of auction of this case" and with respect to the subject matter of auction of this case No. 1 through No. 19, 21 among the subject matter of auction of this case, the Chuncheon District Court No. 11082, Sept. 3, 1997, determined the maximum debt amount as KRW 30 million, the National Forestry Cooperatives Federation (the National Forestry Cooperatives Federation before the modification; hereinafter the "National Forestry Cooperatives Federation"), the National Forestry Cooperatives Federation (the National Forestry Cooperatives Federation) and the National Forestry Cooperatives Federation (the National Forestry Cooperatives Federation, the National Forestry Cooperatives Federation, the National Forestry Cooperatives Federation (the maximum debt amount of KRW 50,500,000,000,000,000 won, KRW 5057,000,000,0000,000 won, and completed the registration of creation of mortgage of this case as the registry office No. 9. 7. 86,5006,786,00,065,0,068.
B. After December 2, 2009, the Plaintiff concluded a gift contract with a mutual savings bank on the preceding day of the date of the auction, and completed the registration of ownership transfer on the same day.
C. On September 14, 2010, the National Forestry Cooperatives Federation received a voluntary decision to commence auction from the original branch of the Chuncheon District Court (hereinafter “instant auction procedure”) from the said court C. On July 27, 2011, the said court en bloc held real estate listed in the attached Table 1 (hereinafter “instant real estate”).