Text
1. As to each of the Plaintiffs’ KRW 101,00,000 and each of the aforementioned KRW 100,000,000, the Defendant shall start on June 8, 2018, and each of the said KRW 1,000.
Reasons
1. Basic facts
A. On December 7, 2015, Plaintiff A Co., Ltd (former B Co., Ltd.; hereinafter “Plaintiff A”) concluded a contract with the Defendant for construction work of constructing an apartment on the south-gu Seoul Southern-gu ground (hereinafter “instant construction work”) by setting the construction cost of KRW 4,025,892,00 (including value-added tax) from December 18, 2015 to February 28, 2017 during the construction period of the construction work period as KRW 0.1% per day per annum (hereinafter “instant contract”). On the same day, Plaintiff C Co., Ltd (hereinafter “Plaintiff C”) concluded a contract with the Defendant for the construction work of newly constructing an apartment on the south-gu Seoul-gu ground (hereinafter “instant contract for construction work”) at the rate of construction price of KRW 3,970,278,00 per day, value-added tax (including value-added tax), and the period from February 18, 2015 to February 28, 2015>
B. From March 16, 2016 to February 9, 2017, Plaintiff A paid KRW 1,899,109,630 as the construction cost of the instant first contract to the Defendant; and Plaintiff C paid KRW 1,464,383,354 as the construction cost of the instant second contract to the Defendant by February 9, 2017.
C. On March 21, 2017, the Defendant sent to the Plaintiffs a letter of content-certified mail and a letter of waiver of construction, stating the intent to waive the instant Nos. 1 and 2 due to the Defendant’s managerial difficulties, etc., respectively. On March 22, 2017, the Plaintiffs sent to the Defendant a letter of content-certified mail stating the Defendant’s declaration of termination of the instant Nos. 1 and 2 contracts, which reached the Defendant around that time.
The Plaintiffs, on April 10, 2017, to G Co., Ltd. (hereinafter “G”), Plaintiff A awarded a contract for the remainder of the instant 1 construction; and Plaintiff C awarded a contract for the remainder of the instant 2 construction; and on December 7, 2018, the approval for use for the instant 1 and 2 construction was granted.
[Reasons for Recognition] Unsatisfy, Gap evidence 1, 2-1 through 4, 3, 4, 5-1, 2, 5-2.