logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2015.01.29 2013가합535085
공사대금
Text

1. The defendant shall pay to the plaintiff Hanyang Development Co., Ltd. KRW 79,416,479, and KRW 52,94,319 and each of the above amounts.

Reasons

In light of the above legal principles, the lower court’s determination on the ground that the Defendant’s refusal to raise an objection against the instant third construction based on the Plaintiffs’ wage payment ledger, etc., and that the Defendant calculated labor costs, industrial accident insurance premiums, general management expenses, value-added tax, etc. required from March 5, 2013 to April 1, 2013, which the Plaintiffs sought during the extended period of the instant third construction, constitutes grounds for 10,635,780 as indicated below [Attachment 1] and [Attachment 2].

The third amount of wages received for the number of working days: 27 days ( March 5, 2013 - April 1, 2013): 27 days ( March 5, 2013 - April 1, 2013). D 273,80,000 head of the construction site office G G G, H 272,968,00, 768,000, 9768, 9768, 975, 97, 97, 97, 968, 97, 97, 968, 97, 168, 168, 160, 160, 168, 160, 160, 160, 280, 160, 280, 395, 209, 97, 97, 209, 196, 1965, 375.

10) (1) The plaintiffs asserted that the period of use of measuring instruments installed to check the stability of surrounding buildings and damage situations due to the extension of the first construction period is extended to 4 months. Thus, the plaintiffs are obliged to additionally pay KRW 7,701,390 to the increased cost of using measuring instruments.

(2) As to this, the Defendant reported the Plaintiff’s change of design via the supervision group.

arrow