(영문) 대구지방법원포항지원 2015.03.31 2013가단303656
사해행위취소
Text

1. On January 29, 2013, the corporeal movables listed in the attached Table 1 list between the defendant and the non-party livestock farming association corporation.

Reasons

1. Basic facts

A. On October 1, 2010, the Plaintiff entered into a contract for the supply of the raw money with the non-party Korean Livestock Farming Association (hereinafter “Korean Livestock”), and continued to supply the raw money. As of January 28, 2013, the Plaintiff had a claim for the purchase of the goods amounting to KRW 2,841,030,151.

B. On December 20, 201, the Defendant entered into a new construction contract with the Korea Livestock Farming Co., Ltd. on the real estate listed in the attached Table 2 (hereinafter “instant building”), and set the construction cost at KRW 1,760,000,000 at the time, but changed the said construction cost to KRW 2,260,000,000 in addition to the contract on December 31, 2012, and completed the said construction work on January 2013.

C. On January 29, 2013, Korea Livestock Co., Ltd. entered into a sales contract with the Defendant for corporeal movables listed in the separate sheet No. 1 (hereinafter “instant corporeal Movables”) and the instant building (hereinafter “instant sales contract”). On the same day, the registration of ownership transfer was completed for the Defendant on the same day, and the said corporeal movables were handed over to the Defendant.

On the other hand, at the time of the instant sales contract, Korea Livestock Co., Ltd. was liable for a total amount of 14 billion won or more to the Plaintiff and the Defendant, Nonghyup Bank Co., Ltd., New Bank, Seoul Guarantee Insurance Co., Ltd., and the Korea Credit Guarantee Fund. However, as active property, there was a building of this case, the instant corporeal movables and the instant corporeal movables, and a total of 14 billion won or more, and there was a lot of 2175 square meters or more between 1891.9 square meters and 1146.4 square meters and 2186.5 square meters or more at the same time.

[Ground of recognition] Unsatisfy, Gap evidence Nos. 1 through 4, Eul evidence Nos. 1 through 6 (including each number), and the result of this court's order to submit financial transaction information to the Korea Federation of Banks, the Court Administration, the Ministry of Land, Infrastructure and Transport, and the result of each fact inquiry into North Korea at Port, the purport of the whole pleadings, as a

2. Determination

A. According to the facts found in the establishment of the fraudulent act, the Korean livestock industry is in excess of its obligations.

arrow