logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원 2015.06.11 2013구합12752
손실보상금
Text

1. The defendant

A. From July 17, 2013, Plaintiff-ju Livestock Industry Cooperatives (hereinafter “Plaintiff-ju”) KRW 3,317,766,180 and its related amount.

Reasons

1. Details of ruling;

(a) Business authorization and public notice - C Housing site development project (hereinafter “instant project,” and the “instant project zone”) - The Defendant: D public notice of the Ministry of Land, Transport and Maritime Affairs (No. 31, 2008), E public notice of the Ministry of Land, Transport and Maritime Affairs (No. 5, 2012), F public notice of the Ministry of Land, Transport and Maritime Affairs (No. 24, 2012):

B. The Central Land Expropriation Committee’s ruling on expropriation on May 23, 2013 - Each real estate indicated on the details of real estate compensation in attached Form 1 and each obstacles indicated on the details of compensation for obstacles to attached Form 2 (hereinafter “each land of this case” and “the obstacles of this case”) - The date of commencement of expropriation: Compensation on July 16, 2013 - The same shall apply to the amount of adjudication on expropriation among the details of compensation in attached Tables 1 and 2.

- An appraisal corporation: A certified public appraisal corporation and the central public appraisal corporation (hereinafter referred to as “adjudication appraiser”)

C. The Plaintiffs’ legal relationship 1) Plaintiff Pakistan-Yancheon Livestock Cooperatives (hereinafter “Plaintiff Association”)

(2) The court below held the following facts: (a) on June 24, 2013, G, H, I, and the third debtor as the Defendant and the third debtor as the damages claim amounting to KRW 8.26 billion; (b) prior to the above ruling of expropriation, the court below issued an order of seizure and assignment of the damages claim against the third debtor as to the damages claim amounting to KRW 4,942,23,820 (i.e., G’s compensation amounting to KRW 1,398,625,274 (i.e., H’s compensation amounting to KRW 3,471,592,350,000,000,000 G, and KRW 1,260,000,000,000,000 won; and (iii) on June 24, 2013, the court below issued an order of seizure and assignment of the damages claim amounting to KRW 1,361,0361,20636

arrow