logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 인천지방법원 2015.11.25 2015가단2903
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 41,619,00 and the interest rate of KRW 15% per annum from January 23, 2015 to the day of complete payment.

Reasons

1. Comprehensively taking account of the overall purport of Gap evidence Nos. 1 through 8 as to the cause of the claim, the plaintiff was a company operating the electricity business, fire fighting system construction business, etc.; the defendant registered its business under the name of his wife C; the plaintiff paid the plaintiff 5,00,00 construction cost for the electricity and network construction work (hereinafter "the construction work of this case") in Gwangju City E-si, Gwangju; the period of construction of the 50,000,000 construction cost (including value-added tax); the defendant paid the plaintiff 2,000,000,000,000 won to the plaintiff 10,000,000,000 won to the plaintiff 2,000,000,000,000,000,000,000,000,000,0000,000,000,000,000,000,000,000,00.

arrow