Text
1. The Defendant: (a) KRW 225,041,00 for the Plaintiff and 5% per annum from November 11, 2015 to August 30, 2017.
Reasons
1. Details of ruling;
(a) Business authorization and public announcement - Railroad construction project authorization (hereinafter referred to as "project in this case") - Project operator: Defendant - Public announcement of project implementation authorization: C public announcement of June 13, 201 and D public announcement of June 28, 2013, E of the same public announcement on April 2, 2014, and February 2, 2015.
B. The Central Land Tribunal’s ruling of expropriation on September 17, 2015 - Expropriation date: The expropriation date: November 10, 2015 - Before Ulsan-gun, Ulsan-gun, Ulsan-gun, the Plaintiff’s ownership, the sum of 14 square meters and 94 square meters prior to H (hereinafter “each expropriation land of this case,” the individual land shall be specified as the lot number): The Plaintiff’s determination as to the Plaintiff’s assertion: The Plaintiff’s total sum of 382 square meters prior to Ulsan-gun, Ulsan-gun, the JJ, the 75 square meters prior to KM, and 136 square meters prior to K (hereinafter “each remaining land of this case”; the individual land is specified as the lot number; the location of each remaining land of this case and each remaining land of this case shall be the same as the attached Table 1). However, the Plaintiff asserted that the remaining land of this case is used as the site of the building adjacent to each of the instant case, and that some of the existing building is scheduled to be 30 square meters of each of this case (hereinafter.).
C. On July 23, 2014, 14 square meters out of the above land is G land and 94 square meters is H.