(영문) 대전지방법원천안지원 2019.04.03 2019가단131
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 45,900,000 as well as KRW 43,900,00 among them, from December 11, 2018 to the day of full payment.

Reasons

In full view of the purport of the argument in Gap evidence No. 1, the plaintiff entered into a contract for C Corporation with the defendant on August 21, 2015, and on February 1, 2016, the defendant agreed to pay the plaintiff the balance of 43,900,000 won and interest of 2,90,000,000 won and interest of 45,90,000 won to the plaintiff until March 31, 2016. According to the above facts of recognition, the defendant is obligated to pay the plaintiff the above balance of the construction and interest of 45,90,000 won and interest of 43,90,000,000 won with the exception of interest of 43,00,000 won and interest of 43,90,000 won with the delivery of a copy of the complaint of this case from December 11, 2018 to the day of full payment.

The plaintiff's claim is reasonable, and it is so decided as per Disposition.

arrow