logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 춘천지방법원원주지원 2016.09.29 2016가합93
공사대금
Text

1. The Defendant’s KRW 399,341,550 as well as the Plaintiff’s annual 6% from January 31, 2014 to January 13, 2016, and the following.

Reasons

1. On May 21, 2013, the construction period for the construction project name No. 1, 201, the date of the contract, concluded an additional construction contract with the Defendant on May 23, 2013 to June 13, 2013, 160,000 or August 13, 2013 to August 2, 2013 to 264,000,000,003 to 30,000 or less, and the Plaintiff concluded an additional construction contract with the Defendant on September 3, 2013 to 13, 205, each of the following additional construction contracts with the Defendant on September 3, 2013 to 30, 15, 2013: (a) the additional construction contract with the Defendant on September 3, 2013 to 49, 518, 50, 2013 to 13, 15,2013.

[Reasons for Recognition] Unsatisfy, entry in Gap evidence 1 and 2 (including provisional number), the purport of the whole pleadings

2. According to the above facts of recognition, the defendant is obligated to pay to the plaintiff 39,341,550 won remaining after deducting 113,00,000 won which the plaintiff had already received at the construction cost of KRW 512,341,550, and damages for delay calculated at the rate of 15% per annum under the Commercial Act from January 31, 2014 to January 13, 2016, the delivery date of a copy of the complaint of this case, which is the delivery date of the copy of the complaint of this case, and from the following day to the day of full payment, the damages for delay calculated at the rate of 15% per annum under the Act on Special Cases concerning the Promotion, etc. of Legal Proceedings.

3. In conclusion, the plaintiff's claim of this case is reasonable, and it is so decided as per Disposition.

arrow