(영문) 대전지방법원천안지원 2015.12.30 2015가단110894
구상금
Text

1. As to KRW 21,089,403 and KRW 20,965,335 among the Plaintiff, the Defendant shall pay to the Plaintiff the year from September 14, 2015 to October 21, 2015.

Reasons

1. Indication of claims: To be as shown in attached Form of claims;

(4) The court below held that the plaintiff's assertion was all led to the confession pursuant to Article 150 of the Civil Procedure Act (Article 208 (3) 2 of the Civil Procedure Act), since the plaintiff submitted a written objection with the original copy of the payment order, and the defendant did not attend the court on the date of pleading without submitting any specific written response.

3. The statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings (Presidential Decree No. 26553, Sept. 25, 2015; Presidential Decree No. 26553, Oct. 1, 2015) was set at 15% per annum under the main sentence of Article 3(1) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings

Therefore, there is no reason to claim damages for delay calculated at the rate exceeding 15% per annum of the damages for delay from the day following the delivery of the original copy of the payment order of this case.